FEMA's compliance process includes twenty sequential steps and many stages which LUMA endeavors to fully complete while meeting established timelines. The process includes communications with various stakeholders, requesting and receiving approvals, where required, and constant review of the project parameters and goals. At a high level, the initial step involves preparing an initial Scope of Work (“ISOW”) with functional specifications and cost estimates. That ISOW then goes through an extensive review and approval process. Once the ISOW gets approved internally, it is filed with the PREB for review and approval, in compliance with the Resolution and Order of March 26, 2021 (the “March 26 Order'') part of the NEPR-MI-2021-0002 docket and in alignment with the Puerto Rico Electric Power Authority (“PREPA”) Integrated Resource Plan (“IRP”) and Modified Action Plan. If LUMA receives PREB approval for the project, then LUMA proceeds to initiate the project with COR3 and FEMA to initiate the approval process. FEMA evaluates the ISOW and, if approved, assigns a FEMA Accelerated Awards Strategy (“FAASt'') number.
FEMA 的合规流程包括几个连续步骤和多个阶段,LUMA 全力参与其中,同时满足既定的时间表以实现联邦资助的项目目标。该流程包括但不限于与各个利益相关者的沟通、在需要时请求和获得批准以及不断审查项目参数和目标。从高层次来看,初始步骤涉及准备初始工作范围(“ISOW”),其中包含功能规范和预测成本估算。然后,该 ISOW 经过广泛的审查和批准流程。一旦 ISOW 获得内部批准,就会提交给 PREB 进行审查和批准,以符合 NEPR-MI-2021-0002 档案中的 2021 年 3 月 26 日决议和命令(“3 月 26 日命令”)部分,并与波多黎各电力管理局(“PREPA”)综合资源计划(“IRP”)和修改后的行动计划保持一致。如果 LUMA 获得 PREB 对项目的批准,则 LUMA 将与 COR3 和 FEMA 一起启动该项目,以启动审批流程。FEMA 评估 ISOW,如果获得批准,则分配 FEMA 加速奖励策略(“FAASt”)编号。
• 通过配电杆导体和维修、变电站、输电线和输电优先杆更换计划,为 129 个 FEMA 义务项目通电。• 获得 FEMA 对 146 个项目的义务,估计投资额为 21 亿美元,以及 10.6 亿美元的建筑和工程 (A&E) 和 6.56 亿美元的长周期材料采购。• 向 COR3 和 FEMA 提交了总共 346 份详细工作范围 (DSOW) 以供批准,估计投资额为 98 亿美元。• 与 COR3 和 FEMA 一起启动了总计 395 个输电和配电项目 (T&D 项目),估计重建活动金额为 117 亿美元。• 向波多黎各能源局 (PREB) 提交了初步工作范围 (ISOW),共涉及 226 个项目和计划2,代表 LUMA 正在推进的重建工作,预计耗资 150 亿美元。